Ensa successfully loads the first two ENUN 32P casks in Trillo NNPP

2019-01-24T08:21:51+00:00

Maliaño, January the 24th of 2019. – Equipos Nucleares S.A., S.M.E (Ensa) successfully completed the loading of the second ENUN 32P cask at Trillo Nuclear Power Plant in Guadalajara. The cask was transferred to its storage position in the Individual Spent Fuel Storage Installation (ISFSI of the plant, where 2 ENUN 32P casks and 32 DPT casks, also designed, manufactured and loaded by Ensa, are stored.

With the loading of these casks, carried out in collaboration with Enwesa S.A., S.M.E, a subsidiary of Ensa, the first load campaign of the ENUN 32P casks was successfully completed and the process of starting up was completed. This process was previously initiated by the modification of auxiliary equipment and the performance of cold trials.

ENUN 32P casks, designed and manufactured by Ensa, allow the transport and storage of spent fuel. These first campaigns of loads carried out in Almaraz NNPP and Trillo NNPP suppose putting in service this cask model of the ENUN series.